Weather was bound to get to us eventually, it is the last week of January. The rain the other day brought the lake up 3’-9”. (Not sure how much rain we did get, as my gauge cracked, but it was quite a bit). And some snow today, up to 2” […]
BRIDGE UPDATE Our bridge project is moving into the last phase. On Tuesday, January 12, the five concrete beams were placed on the two bents. We have been extremely lucky thus far with weather and depth of water. Wayne Brenneke Construction is placing the rebar for the topping slab […]
#letsbuildabridge !!!! Unfortunately, we received quite a bit of rain in the last few weeks which brought the water level up very quickly. The water was too high to hit our target date of December 1 to begin demolition of the bridge. But after meetings with our contractor, we are […]