The following report for Lake, Dam & Spillway was provided by Dale Brunts (Chairman Lake, Dam & Spillway). Should you have any questions you can email Dale at bod.dbrunts@ilpoa.org.


Buoys were set as follows:

  • Cove 1:  2 buoys
  • Cove 2:  1 buoy
  • Cove 3:  1 buoy
  • Cove 4:  1 buoy
  • Cove 5:  1 buoy
  • Cove 6:  1 buoy
  • Cove 7:  2 buoys
  • Swim Area:  3 buoys
  • Entrance to marina:  1 buoy  
  • #37 Lakeshore:  1 buoy
  • #584 Lakeshore:  1 buoy