Road & Maint

October 28, 2019

Exit Road Detour

We have worked carefully to create a safe separation of the exit road using safety cones in order to allow both incoming and outgoing traffic for our members and guests.  Unfortunately beginning on 10/24 we began to lose safety cones either through theft or running over them and not taking […]
October 24, 2019

Entrance Road Closure (10/22-11/4)

First, thanks to all of our members who have patiently navigated using our exit lane for entering and exiting the community while work continues on the entrance road. We are looking forward to seeing how beautiful our entrance will look after all work is done.  After talking to our contractor […]
September 19, 2019

Dam Road Open & It is Lookin’ Good!

Tonight (Thursday evening by 9 p.m., September 19th) the Dam Road is back open and ready for normal traffic. John Richmond is coordinating to make sure the School District Transportation Department and Emergency Services are notified that the road is open again. I want to thank John Richmond (ILPOA Board, […]
September 17, 2019

We’re Working For You!

We have been communicating recently on two improvement projects for the community: Entrance Road and Dam Road Replacement. We wanted to provide you with some pictures of these projects so you can see what is happening. It is exciting to see projects happening in our community but we are not […]
September 13, 2019

Dam Road Will Be Closed Monday (16th) – Tuesday (17th)

N. B. West will be replacing the dam road beginning Monday, September 16th and anticipate completion of the project by end of day Tuesday, September 17th (weather permitting). As a result the dam road will be closed to all traffic while the road work is in progress. The ILPOA Office […]
September 10, 2019

Entrance Road Update (9/10/19)

Attention Members As you can see when you enter the community the work has started on our entrance road.  We want to urge our members, guests and vendors to slow down when you approach the work area and be careful for not only yourself but also the safety of our […]
August 28, 2019

Roads & Maintenance Update – Entrance Road

We have received numerous positive comments regarding the work recently completed on the exit road.  In addition, many of our members indicated they were anxious for us to complete the work with our entrance road.  Our entrance and exit roads are the heaviest use roads in our community in addition […]
August 17, 2019

Gate/Entrance Update

I would like to inform you about what is happening at the exit road and entrance roads. On 8/12/19 the final leg of the exit road was wrapped up.  Our gate company wrapped up the installation of the new exit road gate arm just behind the exit slide gate.  This […]